The Outside is coming along

The siding is going on!!
The 2x6 at the top of the vinyl will get wrapped with white metal/vinyl and then white board and batten siding will go in the gable.

The upstairs dormer


Another shot of the upstairs dormer


The rear of the house


The far side of the house with the rear nursery/study area


The far right side of the house








We are getting there

The Kitchen (there will be a bar height countertop on the beadboard knee wall)

The island will all be at one level...the base isn't built yet for one side.




The Master Bath


The Master Bath Vanity


Window Trim detail.

Interior Door Style

Exterior door from the inside


Exterior Door from the outside.











Monday, October 12, 2009

Micro Hood Vent



The line on the right is at the upper edge of the cabinets and the venting is several inches proud of that line.

On the right side the venting is flanked by a 2x4 and on the left side by the wire for the microhood.
from the face of the current 90 to the front of the wall is approximately 3 inches
The full depth of the wall in nearly 5" thick (the depth of a 2x4, the OSB sheathing, and the sheetrock).


Below is a rough sketch of the proposed periscope.
























Thursday, September 24, 2009

Now I can have a garage band











For those about to Rock...we salute you

Before

After
Before
AfterBefore
After


Sometimes when talking about hanging sheetrock or drywall people simply refer to it as "rocking." Applying the tape and mud is sometimes called "slinging mud." Therefore I can say that I we have been "hanging, rocking, and slinging mud." What fun!!
















Friday, September 4, 2009

The laying of the pipe

Before
After


Waste Tube was still past the wall and will interfere with sheetrock install, but the plumber pulled it back with a metal strap.